South Pars 18-Ich Off-Bottom Tow Project
Print
Joomla 2.5 темы
календари и события для Joomla

PROJECT NAME : South Pars 18-Ich Off-Bottom Tow Project LOCATION : Middle East
BUSINESS AREA : Subsea & Offshore Technology DURATION : 8-Months
CATEGORY : Pipeline Tow Methodology OPERATOR : POGC
CONTRACTOR : IOEC

PROJECT DESCTIPTION:
The South Pars Gas field development comprises the development of an offshore reservoir, located approximately
100km South-West of Assaluyeh. The reservoir contains gas condensate. The South Pars reservoir is to be
produced from a Production platform and two well head platforms.
The focus of this project will be the construction and installation of the Infield Flowline Only. The infield flowline
consists of the pipeline and riser sections, tie-in spool pieces and the integrated piping componets between the pig
traps on the satellite Wellhead platform SPD2 and the Production platform SPP1.

SCOPE OF WORK:
PROJECT MANAGEMENT ACTIVITIES
This involves the control of all activities and ensures that all work is in
compliance with QA/QC procedures and are completed at specified
milestones and are within the agreed budget.
PROCUREMENT ACTIVITIES
This involves the preparation of requisition forms for items to be procured
and technically evaluate the bids that are received from the vendors. This
will be conducted in parallel to specified milestones.
CONSTRUCTION ENGINEERING
Carry out the engineering analysis required for the onshore site
preparation to safely construct pipestrings to be installed offshore. This
will include the Preparation of relevant reports, analysis, specifications
and procedures for the onshore activities.
INSTALLATION ENGINEERING
Carry out the engineering analysis required for the offshore tow
installation methodology to safely transport the pipestrings to be
appropriate location offshore. This will include the Preparation of relevant
reports, analysis, specifications and procedures for the offshore activities.