Qeshm Submarine Water Pipeline Project
Print
Joomla 2.5 темы
календари и события для Joomla

PROJECT NAME : Qeshm Submarine Water Pipeline Project LOCATION : Middle East
BUSINESS AREA : Subsea & Offshore Technology DURATION : 6-Months
CATEGORY : Offshore Pipeline System OPERATOR : Hormozgan
CONTRACTOR : SADRA


PROJECT DESCTIPTION:
Qeshm submarine water pipeline project consists of the installation of approximately 9.831km of a 28 inch
pipeline from west side of shipyard complex at Bandar Abbas to Qeshm Island. The earlier proposed Qeshm
Island landing point located near to Kovehi port has lead to a crossing of an anchorage area. In July 2003,
Hormozogan Regional Water Company decided to move the landing point at Qeshm Island to Ra’s-e Zeynabi
which is located at the South West of the Kovehi port. The change allows the new pipeline route to avoid the
Kovehi Port anchorage area as well as the port limit area.

SCOPE OF WORK:
PIPELINE DETAILED DESIGN
This involves the mechanical design of the water pipeline, and comprises of,
but not limited to the following activities:
• Pipeline Route Selection
• Material grade and Wall Thickness
• On-Bottom Stability
• Span Analysis
• Expansion
• Cathodic Protection (CP) design
• Bottom Roughness and Institu Analysis